SpellerMetcalfe

Achieving Airtightness


The airtightness of a structure relates to the rate at which air escapes from it, measured in m³/m²/hour.  It is important to differentiate between airtightness and ventilation; ventilation involves the controlled exchange of air in a building structure whilst air escaping through other routes is uncontrolled.  The airtightness of a building is extremely important in terms of a structure’s energy use as the faster air escapes from a building the faster heat escapes. Therefore the less airtight a building is the more energy is needed to heat it.

Current UK Part L Building Regulations require new buildings to achieve an Airtightness of 10m³/m²/hour.  This is comparably miles away from the stringent airtightness parameters required to achieve Passivhaus buildings and other sustainable structures.  Our Code for Sustainable Homes Level 6 project achieved and airtightness test result of 0.97 m³/m²/hour meaning that the building fabric was some 27 times better than the average building  in the UK.

One of the main barriers to achieving better airtightness in buildings is that lack of knowledge in the construction industry both in terms of airtight design philosophies and the physical construction of airtight buildings.  Often, if airtight design and construction issues are not addressed at an early stage of the project then there is a significant risk that the building could fail to reach a specified airtightness, or even comply with building regs.


  In accordance with best practice philosophies and our own experience we have developed the following simple strategy to help ensure better airtightness:

  1. Set a target for the air permeability rate & ensure that a comprehensive design review of airtightness strategy takes place to ensure that the method for ensuring an airtight barrier is identified; for example an airtightness membrane, such as Pro Clima Intello could be specified.  Air leakage design review workshops could further develop detailed design, whilst including the airtight envelope as a red line on drawings will highlight it’s importance.  Finally ensure that the air permeability requirements are written into project specifications so that the figure required is perfectly clear to all involved with the project.  

  2. Ensure that airtightness requirements are clarified when placing subcontract work orders and that the airtightness target and methods for achieving are included in the site induction procedures so that all trade persons are aware.

  3. Prior to construction commencement appoint an ‘airtightness champion’ who will oversee all works that will have an impact on airtightness.  This person could be the project manager, or a skilled tradesman working on the project. They will be charged with the duty of overseeing the quality of all works associated with airtightness, and for bringing airtightness issues to the awareness of others working on the build.

  4. Implement an airtightness quality control checking procedure to enable sign off for different areas of the building once the airtightness envelope works are complete; this will be controlled by the airtightness champion.

  5. If possible carry out pre-completion testing of the airtightness envelope prior to the formal air test.  Speller Metcalfe use small scale air pressure fans and ‘smoke’ pens to facilitate this process.  Weak points in the building envelope can be identified and made good prior to the formal test, meaning that the end result will be better.

  6. Carry out the formal airtightness test using a certified air test company.  On the day of the test double check the building to ensure that all external doors and windows are firmly closed.  Additionally check that all routes for planned air exchange such as ventilation ducts are temporarily taped over; the same applies to waste ducts (toilets & sink drains)  if the drain traps are not filled with water.  Accidentally leaving a ventilation duct uncovered could make a massive difference to the end test result.

Speller Metcalfe can help you apply this failsafe philosophy to your project throughout the whole design & build process.  Please do not hesitate to contact us for impartial advice on your project.


Powered by micms